Montoyer 47 – CPE “No Cure No Pay”

Building

  • Assignment: Offices
  • Area: 11,098 m²

Actors

  • Client: Generali
  • Design office: Deplasse & Associates
  • Technical operator: Veolia
  • Property Manager: Cushman & Wakefield

Assignment

  • Technical support for thermal discomfort issues
  • Thermographic analysis of terminal units
  • Regulation optimization
  • Implementation of a “No Cure No Pay” CPE
  • IPMVP Compliant Monthly Energy Tracking

40% fuel economy

20% electricity saving

Annual gain > €35,000

The mission began with technical assistance to solve thermal discomfort problems. After analyzing the energy consumption, it seemed to us that it was abnormally high for a recently renovated building. We therefore offered the client a regulation optimization mission in the form of a “No Cure No Pay” Energy Performance Contract for a period of 1 year. Our remuneration is therefore directly linked to the savings achieved by the actions to optimize the regulation of technical installations.